Here is the information that I can provide at this time for the STH 47 construction project.
-MCC will be coming in soon to prep and pave the utility trenches
-Striping the road should follow once paved
-Final cleanup and sweeping the road with minimal touch up of restoration around paved driveways.
This will complete the village’s portion of the utility work.
This puts the Hwy opening sometime the week of August 19th ahead of the projected completion date of August 30.
The Hwy will be open through the Labor Day holiday.
On Sept. 3rd the State D.O.T. will be doing a closure of the Hwy for 30 days to do storm water restoration work.
These dates could change depending on weather conditions.
Thank you for your patience and understanding throughout this project
Please call with any questions,
Steve Hackl,
Black Creek DPW
920-419-5333